Preparatory work for the Blue line extension will begin in the Langelier/Jean-Talon area during the week of August 7, 2023. The work will involve relocating urban public utilities for the massive excavation that will be needed to build the new métro station. The utilities that need to be relocated include water pipes, sewers, and underground conduits and cabling.

The work will be carried out in phases to reduce the impact on travel in the area. Work will be done during the day, but streets will remain closed overnight. Detours will be in effect, marked by appropriate road signage. Several bus stops will be closed or relocated. Depending on the phase, this will mainly affect lines 33, 141 and 372. Signage will be put up at the affected stops, and a range of real-time information tools will be available to inform users of detours in effect and help them plan their trips. Access to neighbouring businesses will be maintained at all times.

Street closures by phase 
Preparatory work: 1 week
  • Jean-Talon Street: One lane open in each direction
  • Langelier Boulevard: All lanes open
Phase 1: 7 to 8 weeks
  • Jean-Talon Street: Open to westbound traffic on the other side of the street / One lane open in each direction coming from the west
  • Langelier Boulevard: Righthand southbound lane closed /All northbound lanes open
Phase 2: 5 to 6 weeks
  • Jean-Talon Street: Westbound lane fully closed at Langelier Boulevard only / One lane open in each direction coming from the west
  • Langelier Boulevard: Southbound left-turn lane closed / Northbound right-turn lane closed
Phase 3: 1 week
  • Jean-Talon Street: One lane open in each direction
  • Langelier Boulevard: All lanes open

The work will then continue until the end of the year but will not impact vehicle or pedestrian traffic.

Stay informed and be prepared

Visit www.stm.info/plb-langelier to find out more about the Blue line extension and the upcoming preparatory work. The page includes short informative videos where STM experts explain what kind of work will be done and what street closures and mitigation measures will be in place.

The REM ready to welcome first passengers
Line 3 Scarborough to remain closed for at least t...