Snapshot Updates

Snapshot of Lincoln Fields Station - March 20, 2021

 Station construction continues at Lincoln Fields. The first photo below is of the temporary bus loop that was constructed to allow for demolition of the original bus station's local platforms. 

The future LRT station site.
The rail flyover that will split Line 1 and Line 3.
The flyover, to allow for Line 3 bound for Moodie to cross over Line 1, which heads towards Algonquin.

Snapshot of Uplands Station - March 13, 2021

 Construction at Uplands Station continues, adjacent to the EY Centre. Station form work is proceeding. This station will feature double platforms, and will be elevated, with the entrance underneath.

Snapshot of Algonquin Station - March 11, 2021

Work at Algonquin Station (Baseline) continues with excavation to build one of the station entrances. You can see the already existing station tunnel underneath the road, that was previously constructed at the same time Algonquin College built the ACCE building above.

Snapshot of Ellwood Diamond - March 8, 2021

As part of the Stage 2 O-Train Trillium Line South Extension project, work is proceeding on the Ellwood Diamond rail bridge, which will allow VIA Rail trains to safely pass below the Trillium Line. 

Snapshot of Walkley Station - March 8, 2021

Future Walkley Station as seen from the Walkley overpass. The foundation of the station platform can be seen under construction in the middle of the photo. Track and guideway will be found to the right.