Stage 2 LRT Construction Update - FEDCO - December 17, 2021

Committee receives construction update on Stage 2 LRT

The City's Finance and Economic Development Committee received an update today on the three extensions of the Stage 2 LRT project, to the east, west and south.

In the south, work is progressing at the Walkley Maintenance and Storage Facility and on multiple bridges, with girder installation underway at the Ellwood Diamond and Hunt Club rail bridges. Station construction has begun at all sites to the south. The first Stadler vehicle has been delivered and assembly is underway. The remaining vehicles will arrive in 2022.

In the east, Highway 174 roadwork is underway, and utilities are being relocated to make way within the centre median for LRT infrastructure. Construction has started on four of the five planned LRT stations. Construction of the East Rail Flyover bridge and Montréal Station bridge has been completed.

In the west, work continues at the Moodie Light Maintenance and Storage Facility, as well as at Queensview, Iris and Lincoln Fields stations, and along Byron Linear Park. Work is progressing at the slurry plant at Rochester Field and the Sir John A. Macdonald Parkway. Cut-and-cover tunnel construction is underway on the Byron Linear Park Tunnel and the Parkway Tunnel, which will run between Kìchì Sìbì and Lincoln Fields stations travelling under the Sir John A. Macdonald Parkway.

The Committee received an updated schedule outlining the anticipated substantial completion dates for the three extensions. The COVID-19 pandemic has had impacts on major construction projects across Ontario, and City staff are closely monitoring construction schedules and any anticipated delays as a result. The Committee was informed that the O-Train South extension is now anticipated to open in spring 2023, as a result of contractor delays, which pushes out the original schedule of summer 2022. The O-Train East Extension is tracking toward its anticipated completion date in 2024. The O-Train West Extension has some pressure on its scheduled completion date of 2025, but the City and contractor are working together to resolve the critical timelines.

The Committee also approved the acquisition of 3101 Albion Road from the Canadian Pacific Railway, for possible future expansion of the Walkley Maintenance and Storage Facility. The Committee also delegated authority to the director of the rail construction program to negotiate and carry out both station construction and operating agreements for the Airport Link with the Ottawa Macdonald-Cartier International Airport Authority.

Source : City of Ottawa


FEDCO Stage 2 LRT Update - December 17, 2021.mp3

Stage 2 LRT - Construction Photos 

East Extension

West Extension

South Extension


It's finally here... the Rail Fans Canada System M...
Memo: O-Train Light Rail Transit Line 1 and Line 2...